CITY of RAPID CITY

Agenda Item Summary

 

Meeting Date: 3/26/2013

Commission, Board or Committee: N/A

Staff Contact: Rod Johnson

Public Works Committee

Petitioner: City of Rapid City

City Council Meeting: 4/1/13

Location: Multiple

 

Agenda Title:

Change Order #2 to Pendo’s Construction for 2011 Storm damage Recovery Project – Schedule B, Project No. 12-2016B, for an increase of $13,661.04.

Summary:

This change order includes several items encountered during construction that were not covered by the insurance claim but are necessary for a complete and proper installation. Examples include extra shingles, replace roof decking, extra flashing, painting, etc.

Funding Source & Fiscal Impact (if applicable):

CIP Government Buildings

Recommendation:

Action: Choose an item. Approve

Notes: Click here to enter text.

Options:

Click here to enter text.

Attachments & Links:

Change Order

Click here to enter text.

Click here to enter text.